Planning for the new Centre Grey Hospital is proceeding well.
- The hospital’s Project Team is receiving comments on the Master Plan/Program submission from the Ministry of Health and Long Term Care
- The MOH feedback will assist the Project Team in finalizing the Functional Program that is scheduled to be submitted in early September 2007
- The Functional Program contains details on all hospital services, staffing and space requirements
- The Functional Program represents a key milestone in the project and must be approved by the MOH for the project to proceed to implementation